New Westminster Secondary School Replacement Project

Project Description

The Westminster Secondary School Replacement Project accommodated 1,900 grade 9 to 12 students. The school provided a state-of-the-art learning environment. It was designed to optimize the use of flexible learning spaces to maximize collaboration and active learning and include technology that enriches the learning process. Multi-purpose spaces and modern shops, as well as contemporary fine and performing arts spaces enhance the environment for the school community. It also meets today’s standards for modern learning, safety and accessibility, and incorporate the latest sustainable energy and waste management systems. The Project  included a facility that is approximately 19,800 m2 (building gross area) including:

  • Learning space;
  • Parking for staff, students and visitors;
  • Field / outdoor athletic space; and
  • Flexibility to allow for future expansion.

The school was constructed using a design-build procurement approach. 

Project Status:

Completed December 2020

Client:

The Board of Education of School District No. 40

Project Cost:

$106.5 million

Partner:

Graham Design-Builders LP

Project Milestones

Request for Qualifications Issued
November 25, 2016
Request for Qualifications Closed
January 25, 2017
Shortlist Announced
March 8, 2017
Request for Proposals Issued
March 31, 2017
Contract Award
December 9, 2017
Construction Began
Early 2018
Construction Completed
December 2020