Surrey Langley SkyTrain Project (SLS Project) – Guideway Contract

The Surrey Langley SkyTrain (SLS) Project is a 16-km elevated extension of the existing Expo Line primarily along Fraser Highway from the current terminus at King George Station in the City of Surrey, through the Township of Langley to a new terminus station at 203 St. in Langley City Centre.

Surrey Langley SkyTrain Project (SLS Project)

Project Details

Project Description:  The Surrey Langley SkyTrain Project (SLS Project) is a 16-km elevated extension of the existing Expo Line primarily along Fraser Highway from the current terminus at King George Station in the City of Surrey, through the Township of Langley to a new terminus station at 203 St. in Langley City Centre. The Project includes eight new stations, three new transit exchanges, and nine new propulsion power substations.

The SLS Project consists of the following separately procured and staggered contracts:

  1. Guideway Contract – including substructures, superstructures, roadworks, and utilities, procured under a Design-Build-Finance (DBF) model.
  2. Stations Contract – including eight passenger stations, nine propulsion power substations, and 250m of guideway construction at the terminus station, procured under a Design-Build (DB) model.
  3. Systems and Trackwork Contract – including trackwork, power rail and linear induction motor (LIM) rail system, communications, automated train control, and power propulsion equipment, procured under a Target Price model.

 

Client:Ministry of Transportation and Infrastructure
Project Delivered by:Transportation Investment Corporation
Project Cost:The capital cost of Surrey Langley SkyTrain is $3.94 billion. The total project cost, including active transportation investments, is $4.01 billion.
Project Status:The Guideway Contract is in procurement. Expected RFQ launches of Stations Contract is fall 2022, and of Systems and Trackwork Contract is December 2022.
Website:www2.gov.bc.ca/gov/content/transportation-projects/surrey-langley-skytrain
Images:SLS Project Alignment Map
166th St Station conceptual rendering

Guideway Contract Milestones

Request for Qualifications issueAugust 2, 2022
Request for Qualifications closeNovember 1, 2022
Announce shortlisted respondentsJanuary 3, 2023
Request for Proposals issueJanuary 3, 2023
Request for Proposals closeDecember 1, 2023
Contract award2024 (anticipated)
Construction to begin2024 (anticipated)
Construction completed2028 (anticipated)