Burnaby Hospital Project
Burnaby Hospital is a large community hospital which provides a full range of primary and secondary acute care services as well as a number of specialized services.
Burnaby Hospital Project
Project Details
Burnaby Hospital is a large community hospital which provides a full range of primary and secondary acute care services as well as a number of specialized services such as 24/7 emergency care, general and internal medicine, general surgery, orthopedics, gynecology, urology, level one and two obstetrics, neonatal intensive care and tertiary palliative care, adult psychiatry, ambulatory care and other outpatient clinics.
Project Description: Fraser Health Authority is seeking to enter into contracts for Phase 1 of the Burnaby Hospital Redevelopment Project. The scope of the project includes:
- the design and construction of a new six (6) level Inpatient/Outpatient Tower;
- the design and construction of a new five (5) level expansion to the south side of the existing Support Facilities Building;
- renovations to levels 2-4 of the Support Facilities Building, levels 0 and 1 of the Nursing Tower, including select mechanical and electrical elements;and
- demolition of the Cascade and West Wing Buildings;
Client: | Fraser Health Authority |
Project Cost: | The all-in capital cost of the redevelopment of the BH campus (including renovation and expansion costs) is estimated to be approximately $413 million. The construction cost of the Project is estimated to be approximately $390 million. The DBF Scope construction value is anticipated to be approximately $205 million and the CM construction value approximately $185 million. |
Partner: | TBD |
Project Status: | In procurement |
Project Report: | |
Project Website: | Click to access website |
Case Study: | |
Project Image: |
Milestones
Request for Qualifications issued | December 5, 2019 |
Request for Qualifications closed | March 5, 2020 |
Request for Qualifications shortlisted | May 21, 2020 |
Contract award | May 2021 |
Construction to begin | July 2021 |
Construction completed | December 2024 |
Project Updates
Procurement Documents
- Request for Proposals Burnaby Hospital Redevelopment Project – Phase 1 – (June 22, 2020)
- Request for Qualifications Burnaby Hospital Redevelopment Project – Phase 1 – (December 5, 2019)
Project Map
Project Contacts
Jag Tamber
Infrastructure BC
Email: Jag.Tamber@infrastructurebc.com